Each process should be assigned a specific amount of RAM, processors and execution time. There is no one size fits all per se, but a good strategy to begin is requesting more resources than you think you will need, and then reduce as needed.
There are multiple resource tiers defined in conf/base.config
and each module is assigned one of these tiers. You may update these tiers if you wish to modify resources broadly. The resources are described as follows:
Resource | Description |
---|---|
time | The amount of time the process should use. After surpassing this time, the job will timeout. |
cpus | The number of cores to use. A core is a processing unit that executes commands in code. Cores are crucial for parallel processing. |
penv | The parallel environment to use. You will generally never need to change this value. |
memory | The amount of memory to use for the process |
If you look you will notice that each process is assigned different resources:
For example bwa_align is one of the more memory intensive processes and uses 8 cpus, 16 GB of memory, and up to 24 hours. If a task attempt fails, the resources are increased.
withName:bwa_align {
cpus = { check_max( 8 * task.attempt, 'cpus') }
memory = { check_max( 16.GB * task.attempt, 'memory' ) }
time = { check_max( 24.h * task.attempt, 'time') }
}